ORS 540.452 Removal plan approval
An owner seeking to remove a dam that has a significant hazard rating or high hazard rating must notify the Water Resources Department. The owner shall provide the department with a removal plan sufficiently in advance of the removal to allow the department reasonable time for evaluating the plan. The department may evaluate the removal plan to ensure that the plan includes appropriate safety precautions to protect life, property and public infrastructure from temporary inundation in the area below the dam during dam removal. The department may require modification of the removal plan or require that the work performed under the plan be supervised by an engineer to the extent the department concludes is necessary to protect life, property or public infrastructure from temporary inundation during dam removal. If the department requires modification of a dam removal plan or requires that the work be supervised by an engineer, the department shall provide the owner with an opportunity to meet with the department.
A person may not perform removal work on a dam that has a significant hazard rating or high hazard rating except as provided in subsection (1) of this section.
Official sources · 2Tap to view provenance and version history
Provenance
2023 Oregon Revised Statutes
Official online edition
- Source
- oregonlegislature.gov
- SHA-256
ba245de0…e866ce7c- Review
- auto verified
Version history
Prior statutory text is not available in the ingested published editions. Consult an earlier official ORS edition or the cited Oregon Laws chapter.
2025 Oregon Revised Statutes — official online source · active · operative text
Official source2023 Oregon Revised Statutes · active · operative text
Official source