Chapter 543A — Reauthorizing and Decommissioning Hydroelectric Project
ORS 543A.135 Exceptions to final order
(1)
Within 20 days after the Water Resources Director issues a final order under ORS 543A.130 after the conclusion of a contested case hearing, any party may file exceptions to the order with the Water Resources Commission.
(2)
The commission shall issue a modified order, if the exceptions are allowed, or deny the exceptions within 60 days after the close of the exception period under subsection (1) of this section.
Official sources · 2Tap to view provenance and version history
Provenance
2025 Oregon Revised Statutes — official online source
Official online edition
- Source
- oregonlegislature.gov
- SHA-256
cbb93ac4…e9755abb- Review
- auto verified
Version history
Earlier statutory text is available in an ingested published ORS edition.
2025 Oregon Revised Statutes — official online source · active · operative text
Official source2023 Oregon Revised Statutes · active · operative text
Official source