Chapter 279C — Public Contracting - Public Improvements and Related Contracts
ORS 279C.315 Waiver of damages for unreasonable delay by contracting agency against public policy
Any clause in a public improvement contract that purports to waive, release or extinguish the rights of a contractor to damages or an equitable adjustment arising out of unreasonable delay in performing the contract, if the delay is caused by acts or omissions of the contracting agency or persons acting therefor, is against public policy and is void and unenforceable.
Subsection (1) of this section is not intended to render void any contract provision that:
Requires notice of any delay;
Provides for arbitration or other procedures for settlement of contract disputes; or
Provides for reasonable liquidated damages.
Official sources · 2Tap to view provenance and version history
Provenance
2023 Oregon Revised Statutes
Official online edition
- Source
- oregonlegislature.gov
- SHA-256
5b3d61ab…9110657d- Review
- auto verified
Version history
Prior statutory text is not available in the ingested published editions. Consult an earlier official ORS edition or the cited Oregon Laws chapter.
2025 Oregon Revised Statutes — official online source · active · operative text
Official source2023 Oregon Revised Statutes · active · operative text
Official source