Chapter 279C — Public Contracting - Public Improvements and Related Contracts
ORS 279C.315 Waiver of damages for unreasonable delay by contracting agency against public policy
Any clause in a public improvement contract that purports to waive, release or extinguish the rights of a contractor to damages or an equitable adjustment arising out of unreasonable delay in performing the contract, if the delay is caused by acts or omissions of the contracting agency or persons acting therefor, is against public policy and is void and unenforceable.
Subsection (1) of this section is not intended to render void any contract provision that:
Requires notice of any delay;
Provides for arbitration or other procedures for settlement of contract disputes; or
Provides for reasonable liquidated damages.
Official sources · 2Tap to view provenance and version history
Provenance
2025 Oregon Revised Statutes — official online source
Official online edition
- Source
- oregonlegislature.gov
- SHA-256
8acc1879…7bb4d117- Review
- auto verified
Version history
Earlier statutory text is available in an ingested published ORS edition.
2025 Oregon Revised Statutes — official online source · active · operative text
Official source2023 Oregon Revised Statutes · active · operative text
Official source