Chapter 279C — Public Contracting - Public Improvements and Related Contracts
ORS 279C.830 Provisions concerning prevailing rate of wage in specifications, contracts and subcontracts; applicability of prevailing wage; bond
Except as provided in paragraph (e) of this subsection, the specifications for every contract for public works must state the existing state prevailing rate of wage and, if applicable, the federal prevailing rate of wage required under the Davis-Bacon Act (40 U.S.C. 3141 et seq.) that must be paid to workers in each trade or occupation that the contractor or subcontractor or other person who is a party to the contract uses in performing all or part of the contract. If the prevailing rates of wage are available electronically or are accessible on the Internet, the specifications may incorporate the rates by referring to the electronically accessible or Internet-accessible rates and by providing adequate information about how to access the rates.
If a public agency under paragraph (a) of this subsection must state the state and federal prevailing rates of wage in the specifications, the public agency shall also require the contractor to pay the higher of the applicable state or federal prevailing rate of wage to all workers on the public works.
A public works project described in ORS 279C.800 (6)(a)(B) or (C) is subject to the existing state prevailing rate of wage or, if applicable, the federal prevailing rate of wage required under the Davis-Bacon Act that is in effect at the time a public agency enters into an agreement with a private entity for the project. After that time, the specifications for a contract for the public works must state the applicable prevailing rate of wage.
The specifications for a contract for public works must provide that the contractor and every subcontractor must have a public works bond filed with the Construction Contractors Board before starting work on the project, unless the contractor or subcontractor is exempt under ORS 279C.836 (4), (7), (8) or (9).
Every contract that a contracting agency awards must require the contractor to:
Have a public works bond filed with the Construction Contractors Board before starting work on the project, unless the contractor is exempt under ORS 279C.836 (4), (7), (8) or (9).
Require, in every subcontract, that the subcontractor have a public works bond filed with the Construction Contractors Board before starting work on the project, unless the subcontractor is exempt under ORS 279C.836 (4), (7), (8) or (9).
Every subcontract that a contractor or subcontractor awards in connection with a public works contract between a contractor and a public agency must require any subcontractor to have a public works bond filed with the Construction Contractors Board before starting work on the public works project, unless the subcontractor is exempt under ORS 279C.836 (4), (7), (8) or (9).
Official sources · 2Tap to view provenance and version history
Provenance
2025 Oregon Revised Statutes — official online source
Official online edition
- Source
- oregonlegislature.gov
- SHA-256
8acc1879…7bb4d117- Review
- auto verified
Version history
Earlier statutory text is available in an ingested published ORS edition.
2025 Oregon Revised Statutes — official online source · active · operative text
Official source2023 Oregon Revised Statutes · active · operative text
Official source