Chapter 279C — Public Contracting - Public Improvements and Related Contracts
ORS 279C.655 Extension and compensation when work suspended
If a public contract is not terminated but work under the contract is suspended by an order of a contracting agency for any reason considered to be in the public interest other than a labor dispute or any third-party judicial proceeding relating to the work other than a suit or action filed in regards to a labor dispute, the contractor is entitled to a reasonable extension of the contract time and reasonable compensation for all costs resulting from the suspension plus a reasonable allowance for overhead with respect to such costs.
Official sources · 1Tap to view provenance and version history
Provenance
2025 Oregon Revised Statutes — official online source
Official online edition
- Source
- oregonlegislature.gov
- SHA-256
8acc1879…7bb4d117- Review
- auto verified
Version history
Prior statutory text is not available in the ingested published editions. Consult an earlier official ORS edition or the cited Oregon Laws chapter.
2025 Oregon Revised Statutes — official online source · active · operative text
Official source