Chapter 701 — Construction Contractors and Contracts
ORS 701.430 Performance bond; terms
A contractor or subcontractor may execute and deliver to the owner, contractor or subcontractor before the commencement of construction for which the contractor or subcontractor will be responsible for performing a good and sufficient bond in a sum equal to the contract price for the faithful performance of the contract. The term of the bond obtained under this subsection must extend to include the period during which claims of lien or notices of other encumbrances based on the construction performed under the contract may be filed under applicable law. The bond must be approved by the owner, contractor or subcontractor entitled to withhold retainage. A faithful performance bond delivered under this section must include, but not be limited to, provisions to the effect that:
The obligations of the contract must be faithfully performed;
Payment must promptly be made to all persons supplying labor or materials to the contractor or subcontractor for prosecution of the work provided in the contract;
All contributions due the Industrial Accident Fund and the Unemployment Compensation Trust Fund from the contractor or subcontractor in connection with the performance of the contract must be made promptly; and
All sums required to be deducted and retained from the wages of employees of the contractor or subcontractor pursuant to the Personal Income Tax Act of 1969, must be paid over to the Department of Revenue.
Note: See note under 701.410.
Official sources · 1Tap to view provenance details
Provenance
2025 Oregon Revised Statutes — official online source
Official online edition
- Source
- oregonlegislature.gov
- SHA-256
1795680e…503dbac7- Review
- auto verified
Version history
2025 Oregon Revised Statutes — official online source